Section one: Contracting authority
one.1) Name and addresses
Milton Keynes College
Milton Keynes
MK6 5LP
Contact
Craig Pullen
Telephone
+44 7531975978
Country
United Kingdom
NUTS code
UKJ12 - Milton Keynes
Internet address(es)
Main address
one.3) Communication
Additional information can be obtained from the above-mentioned address
one.4) Type of the contracting authority
Body governed by public law
one.5) Main activity
Education
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Refurbishment and Capital Works Improvement
two.1.2) Main CPV code
- 45214300 - Construction work for college buildings
two.1.3) Type of contract
Works
two.1.4) Short description
Program - Works to be carried out between 23 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 05 Sept 2022 - 07 October 2022 [5 weeks]
Adjudication & contractor interviews - 10 - 21 October 2022 [2 weeks]
Second Stage Tender - 24 October 2022 - 02 December 2022. [6 weeks]
Adjudication & contractor appointment - 05 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
two.1.5) Estimated total value
Value excluding VAT: £5,011,966
two.1.6) Information about lots
This contract is divided into lots: No
two.2) Description
two.2.3) Place of performance
NUTS codes
- UKJ12 - Milton Keynes
two.2.4) Description of the procurement
Program - Works to be carried out between 23 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].
The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:
Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]
Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.
Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];
Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.
Tender period - First Stage Tender - 05 Sept 2022 - 07 October 2022 [5 weeks]
Adjudication & contractor interviews - 10 - 21 October 2022 [2 weeks]
Second Stage Tender - 24 October 2022 - 02 December 2022. [6 weeks]
Adjudication & contractor appointment - 05 December - 23 December 2022.
Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON
two.3) Estimated date of publication of contract notice
5 September 2022
Section four. Procedure
four.1) Description
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: Yes