CHARM - Timber Frame Erection and Carpentry

  • ACCORD HOUSING ASSOCIATION LTD

F02: Contract notice

Notice identifier: 2021/S 000-005405

Procurement identifier (OCID): ocds-h6vhtk-029c8e

Published 17 March 2021, 12:37pm



Section one: Contracting authority

one.1) Name and addresses

ACCORD HOUSING ASSOCIATION LTD

178 Birmingham Road

WEST BROMWICH

B706QG

Contact

Mary Doria

Email

Mary.Doria@accordgroup.org.uk

Telephone

+44 7772281019

Country

United Kingdom

NUTS code

UKG - West Midlands (England)

Internet address(es)

Main address

https://accordgroup.org.uk/

one.3) Communication

The procurement documents are available for unrestricted and full direct access, free of charge, at

https://accordgroup.org.uk/

Additional information can be obtained from the above-mentioned address

Tenders or requests to participate must be submitted to the following address:

Accord Housing Association

178 Birmingham Road

West Bromwich

B70 6QG

Contact

Mary Doria

Email

Mary.Doria@accordgroup.org.uk

Country

United Kingdom

NUTS code

UKG - West Midlands (England)

Internet address(es)

Main address

https://accordgroup.org.uk/

one.4) Type of the contracting authority

Other type

Sub-Central Contracting Authority

one.5) Main activity

Housing and community amenities


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

CHARM - Timber Frame Erection and Carpentry

two.1.2) Main CPV code

  • 45000000 - Construction work

two.1.3) Type of contract

Works

two.1.4) Short description

This is a subcontracts package to carry out both the Timber Frame Erection and Carpentry for the CHARM virtually plastic free homes in Redditch, Worcestershire. The main tender information is in the Invitation to Tender document (supplied in PDF and Word versions below).

two.1.6) Information about lots

This contract is divided into lots: No

two.2) Description

two.2.2) Additional CPV code(s)

  • 45000000 - Construction work

two.2.3) Place of performance

NUTS codes
  • UKG - West Midlands (England)
Main site or place of performance

Edward Street, Redditch, B97 6HA

two.2.4) Description of the procurement

The Apartment block is 3 storeys, with 12 Apartments:

• Timber Frame Erection - Eco 200 panels

• First Fix

• Second Fix

• Final Fix

• Soft Pine Skirting and Architrave

• Fire stopping (incl for PODs)

• Fitting fire socks

• Double Battens

• Window former

• Spandrel panels

• Kit Erect/cranes - lifting plans required

• Acoustic Floor

• Internal doors to be door kits, Communal to be pre-hung door sets and Apartment

doors to be SBD timber door sets

• Joists

• Main Roof

• VCL

• Sure deck

• Stairs

• All carpentry works including ironmongery fix

• Ballustrade (Possibly steel)

• Canopies

• Vertical Cladding - The cladding will be secret fixed through the tongue with stainless

steel nails and cut ends of the cladding are to be treated with fire preservative supplied by

the timber merchant

• Final Snagging

• Cavity Barriers

• Fire Protection

• Cranes (include for POD's)

• Cutting out holes (incl for POD's)

• Supply Fixings

• Snag

• 12 Months defects

• Fixed price duration of project

• Customer Care to comply with Accord's Service Level Agreement

two.2.5) Award criteria

Price is not the only award criterion and all criteria are stated only in the procurement documents

two.2.7) Duration of the contract, framework agreement or dynamic purchasing system

Duration in months

9

This contract is subject to renewal

No

two.2.10) Information about variants

Variants will be accepted: No

two.2.11) Information about options

Options: No


Section four. Procedure

four.1) Description

four.1.1) Type of procedure

Open procedure

Accelerated procedure

Justification:

This procurement procedure is an accelerated open procedure as there is urgency in publicity of this tender. This is because we first initially failed to publish this on Contracts Finder as well. Therefore, we had to re-tender this work package and if we were to go through the standard procedure, it will lead to loss of finance due to interest cost on the site and on costs associated with the building site set up. In addition to the grant programme has a number of grant milestones that the additional delay would put at a risk the spending of the EU public funding.

four.1.8) Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: No

four.2) Administrative information

four.2.2) Time limit for receipt of tenders or requests to participate

Date

1 April 2021

Local time

12:00pm

four.2.4) Languages in which tenders or requests to participate may be submitted

English

four.2.7) Conditions for opening of tenders

Date

7 April 2021

Local time

12:00pm


Section six. Complementary information

six.1) Information about recurrence

This is a recurrent procurement: No

six.4) Procedures for review

six.4.1) Review body

Accord Housing Association

West Bromwich

Country

United Kingdom