The Mining Remediation Authority (MRA) has identified the need to construct a mine water monitoring borehole at Brodsworth, Yorkshire. Brodsworth Main Colliery lies within the Barnlsey-Manvers-Grimethorpe sub-block of the South Yorkshire Coalfield, the borehole is to intersect mine workings understood to be flooded with the intention of monitoring mine water levels and chemistry.
The borehole is to be drilled into a roadway in the Barnsley Seam and expected to meet the key requirements set out below.
This initiative aims to enhance the understanding of mine water behaviour in the region and to inform future management strategies.
Key Requirements
The Contractor will be responsible for specific construction details to achieve the borehole requirements, as specified below
Operational time: By March 2026
Methodology: To be selected by the contractor to meet the target requirements
Borehole depth: Estimated 538 - 560metres below ground level (m bgl)
Final internal diameter: Minimum of 100mm
Borehole deviation: 2m from surface location (0.6 from vertical)
Design life: Minimum of 20 years
Headwork: To be completed under a square split lockable manhole cover at surface, minimum of 1000mm x 1000mm with D400 rating.
Minimum of 200mm between base of cover and top of casing. Chamber must be between 0.5 and 1.0 m total depth.
Permits / Land Agreements
The location for the Borehole is identified in a We are in the process of agreeing Head of terms and licence with Land trust to progress with Borehole works. The licence will be formally signed and available prior to site mobilisation in October 2025
Works will be completed under Permitted Development.
Total value (estimated)
- £600,000 excluding VAT
- £750,000 including VAT
Above the relevant threshold
Contract dates (estimated)
- 3 October 2025 to 6 March 2026
- Possible extension to 30 June 2026
- 8 months, 29 days
Main procurement category
Services
CPV classifications
- 76530000 - Downhole services
Contract locations
- UKC - North East (England)
- UKD - North West (England)
- UKE - Yorkshire and the Humber
- UKF - East Midlands (England)
- UKG - West Midlands (England)
- UKH - East of England
- UKI - London
- UKJ - South East (England)
- UKK - South West (England)
Engagement
Engagement deadline
1 August 2025
Engagement process description
The Mining Remediation Authority (MRA) are continuously seeking ways to improve our projects. In the past our delivery partners have drilled a piolet hole first using wireline coring system to maintain the verticality.
A significant risk is the potential for the roadway to differ from expectations, which could lead to missing the intended target. However, this method offers the flexibility to re-drill to an alternative target at minimal additional cost.
We would greatly value your feedback on this proposed approach or a suitable approach to minimise risk and cost of Drilling BH.
Site Visit
Date and time of the Visit: 6th August 2025 at 13.00 - 14.30
Site address: Brodsworth Country Park Car Park, Country Way, Woodlands, Doncaster
DN6 7FR
Please contact: • Jim Moore - Project Manager
Email: Jim Moore
Mob:07827 501 478
To record your interest/attendance
Participation
Particular suitability
Small and medium-sized enterprises (SME)
Contracting authority
Mining Remediation Authority
- Public Procurement Organisation Number: PRPD-5825-QDVY
200 Lichfield Lane
Nottinghamshire
NG18 4RG
United Kingdom
Email: procurement@coal.gov.uk
Region: UKF15 - North Nottinghamshire
Organisation type: Public authority - central government