Tender

Passenger Security Screening Terminal Extension - Project Pegasus

  • BELFAST INTERNATIONAL AIRPORT LIMITED

F02: Contract notice

Notice identifier: 2022/S 000-026445

Procurement identifier (OCID): ocds-h6vhtk-036a3d

Published 21 September 2022, 5:04pm



Section one: Contracting authority

one.1) Name and addresses

BELFAST INTERNATIONAL AIRPORT LIMITED

Belfast International Airport

BELFAST

BT294AB

Email

procurement@bfs.aero

Country

United Kingdom

Region code

UKN0D - Antrim and Newtownabbey

Companies House

NI027630

Internet address(es)

Main address

https://www.belfastairport.com/

one.3) Communication

The procurement documents are available for unrestricted and full direct access, free of charge, at

https://belfastinternationalairport.esourcingportal.com/current_opportunities.cfm

Additional information can be obtained from the above-mentioned address

Tenders or requests to participate must be submitted electronically via

https://belfastinternationalairport.esourcingportal.com/current_opportunities.cfm

one.4) Type of the contracting authority

Body governed by public law

one.5) Main activity

Other activity

Air travel and transport


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

Passenger Security Screening Terminal Extension - Project Pegasus

two.1.2) Main CPV code

  • 45200000 - Works for complete or part construction and civil engineering work

two.1.3) Type of contract

Works

two.1.4) Short description

Belfast International Airport invites expressions of interest in a tender event for the construction of an extension to the terminal building for a new passenger security screening facility (approx 6,000 m sq).

The tender will be published to those expressing interest during this notice period, via the Curtis Fitch eSourcing portal.

two.1.6) Information about lots

This contract is divided into lots: No

two.2) Description

two.2.3) Place of performance

NUTS codes
  • UKN - Northern Ireland
Main site or place of performance

Belfast International Airport

two.2.4) Description of the procurement

The Works will comprise the following:

1. A 2-storey terminal extension to the north east of existing terminal facility. Interfacing with the northside of existing Check In Hall, the east side of the existing vertical circulation core and the north side of the original Terminal building with extensive demolitions and modifications to existing elements to achieve proposed layouts. The proposed building will incorporate:

a. new elevational treatment to better define the front face of Belfast International Airport

b. central search facility

c. improved retail back of house facilities including a ground floor new goods in checkpoint and new goods lifts

d. associated security operational facilities

e. walk through duty free (shell only)

f. new Goods In Waste Away facility

g. new consolidated car hire units and ancillary facilities

h. new arrivals exit hall

i. roof mounted plant

2. External works to include:

a. demolition of existing external canopy to terminal forecourt

b. new canopy to terminal forecourt with improved passenger routing/distribution and associated landscaping

c. relocated taxi rank

d. modifications to existing coach park

e. relocated goods in waste away yard

f. additional HVM

g. works to existing sub-station 2A

3. Primarily landside construction (Approx. 95% landside - 5 % airside)

a. various construction stage interfaces with airside elements along with final transfer of landside site to airside operation

b. contractors compound landside

4. Approx. 90% new build on brownfield site bounded by landside vehicular and passenger movements to the north, goods in yard to the east and the existing terminal to the south.

5. Approx. 10% reconfiguration of existing terminal which includes modifications to the existing Central Search facility (to become new commercial shell unit) and new consolidated car hire units with ancillary facilities.

6. Stage 4 design is finalised and current approx. new build areas comprise:

a. Proposed ground floor new build: approx. 1525 sq.m. (with associated void area beneath first floor)

b. Proposed first floor new build: approx. 3675 sq.m.

c. External canopy: approx. 625 sq.m.

two.2.5) Award criteria

Price is not the only award criterion and all criteria are stated only in the procurement documents

two.2.7) Duration of the contract, framework agreement or dynamic purchasing system

Duration in months

18

This contract is subject to renewal

No

two.2.10) Information about variants

Variants will be accepted: Yes

two.2.11) Information about options

Options: No


Section three. Legal, economic, financial and technical information

three.1) Conditions for participation

three.1.1) Suitability to pursue the professional activity, including requirements relating to enrolment on professional or trade registers

List and brief description of conditions

Experience working in a live airport environment, or similar critical infrastructure environment

three.1.3) Technical and professional ability

List and brief description of selection criteria

ISO 9001: 2015

ISO 45001 (OHSAS 18001)

ISO 14001


Section four. Procedure

four.1) Description

four.1.1) Type of procedure

Open procedure

four.1.8) Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: Yes

four.2) Administrative information

four.2.2) Time limit for receipt of tenders or requests to participate

Date

24 October 2022

Local time

12:00pm

four.2.4) Languages in which tenders or requests to participate may be submitted

English

four.2.7) Conditions for opening of tenders

Date

25 November 2022

Local time

9:00am

Place

Belfast International Airport


Section six. Complementary information

six.1) Information about recurrence

This is a recurrent procurement: No

six.4) Procedures for review

six.4.1) Review body

Belfast International Airport

Belfast

Country

United Kingdom