WO2151 Replacement of Temporary Classrooms at Frogwell, Hullavington and Minety Primary Schools
- Wiltshire Council
Procurement identifier (OCID): ocds-h6vhtk-04f8e8
Description
Wiltshire Council intend to appoint a main Contractor via a two-stage procurement opportunity to deliver an important project on a full design and build basis across three primary schools in Wiltshire.
Stage 1 of the procurement process is to seek expressions of interest from prospective Contractors with a view to shortlisting a maximum of four Contractors to be invited to submit a tender for the project.
Stage 2 of the procurement process will be the Invitation to Tender (ITT) itself.
The Requirement:
The following schools have been identified by the Council as having temporary classrooms which are in a dilapidate state and are in need of replacement by way of either new build developments (Hullavington and Minety), and internal alterations and refurbishment of existing school buildings (Frogwell Primary School):
1. Frogwell Primary School, Chippenham,
2. Hullavington Primary School, Hullavington, Chippenham,
3. Minety Primary School, Malmesbury
The purpose of this procurement opportunity is to appoint a contractor on a full design and build basis, in the first instance operating under a Pre-Construction Services Agreement and working closely with the Schools and the Council through RIBA Work Stages 1 to 4. This Stage 1 appointment will include the following outputs:
1. Operating under a single PCSA to deliver the RIBA Work Stages 1 to 4 inclusive for each of the three schools including.
2. The appointment of a Design Team to work with the School and the Employers Representative to fully design each of the three projects to the end of RIBA Stage 4 (technical/construction design) and to present the design for approval at the end of each RIBA work stage including cost plans for Employer approval,
3. To develop a detailed programme for RIBA Stages 1 to 7 for acceptance by the Employer for each of the three projects,
4. To obtain Building Regulations approval and Planning Permission for each of the three projects,
5. To work collaboratively with the Employers Representative to produce a Fixed Price Lump Sum to deliver the construction works for each of the three projects for approval by the Employer.
On acceptance by the Council of the fixed price lump sum costs to deliver the construction works for each of the three projects, individual construction contracts will be entered into (JCT Intermediate form of contract with Contractor Design) for each school site. These will be the Stage 2 works, and each school project will be delivered as a standalone project through RIBA Work Stages 5, 6 and 7 (Construction, Handover and in Use).
The indicative forecast cost estimate for the Stage 1 pre-construction works is £450k + VAT and the indicative forecast cost estimate of the Stage 2 post contract works is:
Frogwell Primary School £2.0m + VAT = £2.4m
Hullavington Primary School £2.0m + VAT = £2.4m
Minety Primary School £0.75m + VAT = £0.9m
---------------------------
Total Estimated Construction Cost incl VAT £5.7m
Key Programme Dates as follows:
RIBA Stages 1 to 4 End August 25 to End March 26
Package Pricing Stage End March 26 to End June 26
Final Design & Fixed Price Lump Sum Approvals End June 26 to Mid July 26
RIBA Stage 5 Construction Start August 26
Handover To be agreed for each of the school sites during the pre-construction stage of the project
Notices
UK7: Contract details notice
- Notice identifier
- 2025/S 000-075506
- Published
- 20 November 2025, 10:04am
UK6: Contract award notice
- Notice identifier
- 2025/S 000-060443
- Published
- 29 September 2025, 11:55am
UK4: Tender notice
- Notice identifier
- 2025/S 000-014926
- Published
- 14 April 2025, 12:24pm
UK3: Planned procurement notice
- Notice identifier
- 2025/S 000-011315
- Published
- 26 March 2025, 12:49pm