Scope
Reference
343
Description
Stratford Park Lake road runoff diversion project requirements are, the design and build of a new pipe (approximately 90m in length) to connect the existing highway drainage network to the Painswick Stream. The oil interceptors will be kept, the new pipe will connect the outlet from the oil interceptor to a new outfall into the Painswick Stream (aligning with the conditions set out in FRA12 of the environmental permitting regulations) and making good all damaged ground. Please see Project Brief for further information and specification.
Total value (estimated)
- £30,000 excluding VAT
 - £36,000 including VAT
 
Below the relevant threshold
Contract dates (estimated)
- 15 December 2025 to 31 March 2026
 - Possible extension to 30 April 2026
 - 4 months, 17 days
 
Description of possible extension:
one month extension
Main procurement category
Works
CPV classifications
- 45000000 - Construction work
 
Contract locations
- UKK13 - Gloucestershire
 
Participation
Conditions of participation
not required at this value of procurement
Particular suitability
Small and medium-sized enterprises (SME)
Submission
Enquiry deadline
24 November 2025, 5:00pm
Tender submission deadline
1 December 2025, 3:00pm
Submission address and any special instructions
Please review the documents and use the procurement portal messaging system for any clarifications. www.supplyingthesouthwest.org.uk
Tenders may be submitted electronically
Yes
Award criteria
| Name | Description | Type | Weighting | 
|---|---|---|---|
| Price | Price of work  | 
													Price | 80.00% | 
| Quality | Quality areas outlined in Project Brief.  | 
													Quality | 20.00% | 
Procedure
Procedure type
Below threshold - open competition
Contracting authority
Stroud District Council
- Public Procurement Organisation Number: PRHW-3326-HVMG
 
Ebley Mill
Stroud
GL5 4UB
United Kingdom
Region: UKK13 - Gloucestershire
Organisation type: Public authority - sub-central government