Contract

Tunnelling Projects Austhorpe Lane & Ridge Road

  • NORTHERN GAS NETWORKS LIMITED

F06: Contract award notice – utilities

Notice identifier: 2025/S 000-055712

Procurement identifier (OCID): ocds-h6vhtk-02874d (view related notices)

Published 11 September 2025, 11:01am



Section one: Contracting entity

one.1) Name and addresses

NORTHERN GAS NETWORKS LIMITED

1100 Century Way

Colton Leeds

LS158TU

Contact

Harriet Wilkes

Email

hwilkes@northerngas.co.uk

Telephone

+44 7813523683

Country

United Kingdom

Region code

UKE42 - Leeds

Companies House

03528783

Internet address(es)

Main address

www.northerngasnetworks.co.uk

one.6) Main activity

Production, transport and distribution of gas and heat


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

Tunnelling Projects Austhorpe Lane & Ridge Road

two.1.2) Main CPV code

  • 45221000 - Construction work for bridges and tunnels, shafts and subways

two.1.3) Type of contract

Works

two.1.4) Short description

2 contracts are issued following a tender event relating to two separate tunnelling projects.

Project 1 - Ridge Road

Project 2 - Austhorpe Lane

two.1.6) Information about lots

This contract is divided into lots: No

two.1.7) Total value of the procurement (excluding VAT)

Value excluding VAT: £4,363,305.98

two.2) Description

two.2.3) Place of performance

NUTS codes
  • UKE - Yorkshire and the Humber

two.2.4) Description of the procurement

Project 1 - Ridge Road - Relates to the works associated with diverting an approximate 170m length of the Barwick - Knottingley 600NB high pressure (HP) gas pipeline on land to the immediate west of the A656 Ridge Road, approximately 1.6 miles east of Garforth, West Yorkshire. The pipeline operates at an MOP of 38.0bar and is owned & operated by Northern Gas Networks (NGN). Currently the existing pipeline is routed through agricultural land to the north and south of the trans-Pennine railway line and crosses the railway cutting by means of an overhead crossing, supported on a single concrete pillar and full encirclement clamp support to the immediate north or the railway line. It is proposed to divert the pipeline beneath the railway line by means of a micro-tunnelled under track crossing (UTX) in accordance with NGN/SP/G/27, involving the establishment of thrust pit and reception shaft either side of the railway and the installation of a reinforced precast concrete tunnel through which the diverted section of pipeline is to be inserted. This Under Track Crossing will then be utilised later to install a new 600mm Steel H.P pipeline as part of the diversion works.

Project 2 - Austhorpe Lane is a location in Leeds where Network rail plan to demolish a bridge and install new Overhead Electric Lines as part of an upgrade to the rail network. At present 1 x No of 450mm Steel - NGN High Pressure Gas Pipeline is installed as an overcrossing across the Network rail tracks. The current location clashes with the proposed new Network rail Infrastructure and the High-Pressure Gas Pipeline needs to be diverted. This project therefore relates to a design and build package required for installing an Under Track Crossing (UTX) in accordance with NGN/SP/G/27, involving the establishment of thrust pit and reception shaft and the installation of a reinforced precast concrete tunnel through which the diverted section of pipeline is to be inserted. This Under Track Crossing will then be utilised later to install a new 450mm Steel H.P pipeline as part of the diversion works.

two.2.5) Award criteria

Cost criterion - Name: Commercial / Weighting: 40

Cost criterion - Name: Non Commercial / Weighting: 60

two.2.11) Information about options

Options: No


Section four. Procedure

four.1) Description

four.1.1) Type of procedure

Negotiated procedure with prior call for competition

four.1.8) Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: Yes

four.2) Administrative information

four.2.1) Previous publication concerning this procedure

Notice number: 2021/S 000-000006


Section five. Award of contract

Title

Ridge Road

A contract/lot is awarded: Yes

five.2) Award of contract

five.2.1) Date of conclusion of the contract

20 March 2025

five.2.2) Information about tenders

Number of tenders received: 3

Number of tenders received from SMEs: 2

The contract has been awarded to a group of economic operators: No

five.2.3) Name and address of the contractor

Barhale Ltd

Walsall

Country

United Kingdom

NUTS code
  • UKG3 - West Midlands
Companies House

01268005

The contractor is an SME

No

five.2.4) Information on value of contract/lot (excluding VAT)

Total value of the contract/lot: £1,364,362


Section five. Award of contract

A contract/lot is awarded: Yes

five.2) Award of contract

five.2.1) Date of conclusion of the contract

26 August 2025

five.2.2) Information about tenders

Number of tenders received: 2

Number of tenders received from SMEs: 2

The contract has been awarded to a group of economic operators: No

five.2.3) Name and address of the contractor

Terra Solutions Limited

Newry

Country

Ireland

NUTS code
  • IE0 - Ireland
Companies House

NI602210

The contractor is an SME

Yes

five.2.4) Information on value of contract/lot (excluding VAT)

Total value of the contract/lot: £2,998,943.98