Scope
Description
There is a peat pile currently situated in a plot of land required as part of the permanent works on the A57 Link Roads where the new single lane bypass is due to be constructed.
The Peat Pile needs to be moved prior to the project taking possession of the land as once possession has been taken the peat pile becomes the liability for the scheme.
This request is to implement the removal of c6,000m3 of the peat pile currently located within the redline boundary of the A57 Link Road scheme to a location still within the landowner's land but >5m away from the red line boundary.
Contract 1
Supplier
Contract value
- £112,000 excluding VAT
- £134,400 including VAT
Below the relevant threshold
Date signed
27 June 2025
Contract dates
- 9 July 2025 to 30 September 2025
- 2 months, 23 days
Main procurement category
Works
CPV classifications
- 45233130 - Construction work for highways
Contract locations
- UK - United Kingdom
Procedure
Procedure type
Below threshold - without competition
Supplier
C Bower & Sons Limited
Carr House Farm, Carr House Lane,
Hollingworth,
SK14 8NA
United Kingdom
Region: UKD35 - Greater Manchester South East
Small or medium-sized enterprise (SME): No
Voluntary, community or social enterprise (VCSE): No
Contract 1
Contracting authority
National Highways
- Companies House: 09346363
Bridge House, 1 Walnut Tree Close
Guildford
GU1 4LZ
United Kingdom
Email: emma.davis@nationalhighways.co.uk
Website: https://nationalhighways.co.uk
Region: UKJ25 - West Surrey
Organisation type: Public authority - central government