Contract

CO Construction - 132/275kv Substation works ECI - Clash Gour WF - 0625

  • Scottish Hydro Electric Transmission PLC

F06: Contract award notice – utilities

Notice identifier: 2025/S 000-042057

Procurement identifier (OCID): ocds-h6vhtk-02874c

Published 22 July 2025, 2:52pm



Section one: Contracting entity

one.1) Name and addresses

Scottish Hydro Electric Transmission PLC

Inveralmond House, 200 Dunkeld Road

Perth

PH1 3AQ

Email

carrie-anne.causby@sse.com

Country

United Kingdom

Region code

UKM - Scotland

National registration number

SC213461

Internet address(es)

Main address

www.sse.com

one.6) Main activity

Electricity


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

CO Construction - 132/275kv Substation works ECI - Clash Gour WF - 0625

two.1.2) Main CPV code

  • 45232220 - Substation construction work

two.1.3) Type of contract

Works

two.1.4) Short description

The works are the Early Contractor Involvement and associated design, engineering and pre-construction and associated works / services

two.1.6) Information about lots

This contract is divided into lots: No

two.2) Description

two.2.3) Place of performance

NUTS codes
  • UKM - Scotland

two.2.4) Description of the procurement

The works are the Early Contractor Involvement and associated design, engineering and pre-construction and associated works / services

two.2.11) Information about options

Options: No

two.2.13) Information about European Union Funds

The procurement is related to a project and/or programme financed by European Union funds: No


Section four. Procedure

four.1) Description

four.1.1) Type of procedure

Negotiated procedure with prior call for competition

four.1.8) Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: No

four.2) Administrative information

four.2.1) Previous publication concerning this procedure

Notice number: 2021/S 000-000005


Section five. Award of contract

Contract No

33318

Title

CO Construction - 132/275kv Substation works - Clash Gour WF - 3029

A contract/lot is awarded: Yes

five.2) Award of contract

five.2.1) Date of conclusion of the contract

18 July 2025


Section six. Complementary information

six.4) Procedures for review

six.4.1) Review body

SSE PLC

Inveralmond House, 200 Dunkeld Road

Perth

PH1 3AQ

Country

United Kingdom