Section one: Contracting entity
one.1) Name and addresses
NORTHERN GAS NETWORKS LIMITED
1100 Century Way Thorpe Park
LEEDS
LS158TU
Contact
Andrew Christophers
achristophers@northerngas.co.uk
Telephone
+44 7510367358
Country
United Kingdom
Region code
UKE42 - Leeds
Companies House
05167070
Internet address(es)
Main address
https://www.northerngasnetworks.co.uk
one.6) Main activity
Production, transport and distribution of gas and heat
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Redcar Hydrogen Storage Solution (10 Tonnes) - Vessel Supply Only
two.1.2) Main CPV code
- 44615000 - Pressure vessels
two.1.3) Type of contract
Supplies
two.1.4) Short description
Northern Gas Networks (NGN) has been given the go ahead by Government and Ofgem to develop its proposals to create the UK's first hydrogen village. As such the Redcar Hydrogen Community is a proposal from Northern Gas Networks (NGN) to supply around 2,000 homes in an area of Redcar and parts of Kirkleatham with locally produced, clean burning hydrogen from 2025. The hydrogen production capacity will be delivered by the neighbouring Teesside cluster with over 2,500 MW of low carbon hydrogen expected to come online by 2030.
NGN have identified that, to provide a resilient trial, they will require short term storage for intraday changes in demand profile as well as inter-seasonal storage to make up for the difference between summer and winter production and demand profiles.
two.1.6) Information about lots
This contract is divided into lots: No
two.2) Description
two.2.3) Place of performance
NUTS codes
- UKC - North East (England)
two.2.4) Description of the procurement
Northern Gas Networks (NGN) has been given the go ahead by Government and Ofgem to develop its proposals to create the UK's first hydrogen village. As such the Redcar Hydrogen Community is a proposal from Northern Gas Networks (NGN) to supply around 2,000 homes in an area of Redcar and parts of Kirkleatham with locally produced, clean burning hydrogen from 2025. The hydrogen production capacity will be delivered by the neighbouring Teesside cluster with over 2,500 MW of low carbon hydrogen expected to come online by 2030.
NGN have identified that, to provide a resilient trial, they will require short term storage for intraday changes in demand profile as well as inter-seasonal storage to make up for the difference between summer and winter production and demand profiles.
two.2.11) Information about options
Options: No
Section four. Procedure
four.1) Description
four.1.1) Type of procedure
Negotiated procedure with prior call for competition
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: No
four.2) Administrative information
four.2.1) Previous publication concerning this procedure
Notice number: 2023/S 000-030947
Section five. Award of contract
A contract/lot is awarded: No
five.1) Information on non-award
The contract/lot is not awarded
Other reasons (discontinuation of procedure)
Section six. Complementary information
six.4) Procedures for review
six.4.1) Review body
Northern Gas Networks
Leeds
Country
United Kingdom