Section one: Contracting authority/entity
one.1) Name and addresses
BIRMINGHAM CITY COUNCIL
BIRMINGHAM
B4 7WB
Country
United Kingdom
Region code
UKG31 - Birmingham
Justification for not providing organisation identifier
Not on any register
Internet address(es)
Main address
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
A457 Dudley Road Improvement Scheme Update
two.1.2) Main CPV code
- 45233120 - Road construction works
two.1.3) Type of contract
Works
two.2) Description
two.2.3) Place of performance
NUTS codes
- UK - United Kingdom
two.2.4) Description of the procurement at the time of conclusion of the contract:
The design and construction of a large capital improvement scheme to the A457 Dudley Road which is made up of; Heath Street, Dudley Road, Spring Hill and junctions/ side roads.
two.2.7) Duration of the contract, framework agreement, dynamic purchasing system or concession
Duration in months
36
Section four. Procedure
four.2) Administrative information
four.2.1) Contract award notice concerning this contract
Notice number: 2013/S 164-284988
Section five. Award of contract/concession
Contract No
A457
Lot No
4
five.2) Award of contract/concession
five.2.1) Date of conclusion of the contract/concession award decision:
21 October 2019
five.2.2) Information about tenders
The contract/concession has been awarded to a group of economic operators: No
five.2.3) Name and address of the contractor/concessionaire
McPhillips (Wellington) Ltd
Horton House, Hortonwood 50
Telford
TF1 7FG
Country
United Kingdom
NUTS code
- UKG - West Midlands (England)
Justification for not providing organisation identifier
Not on any register
The contractor/concessionaire is an SME
No
five.2.4) Information on value of the contract/lot/concession (at the time of conclusion of the contract;excluding VAT)
Total value of the procurement: £37,102,000
Section six. Complementary information
six.4) Procedures for review
six.4.1) Review body
High Court of Justice
Royal Courts of Justice, Strand
London
WC2A 2LL
Country
United Kingdom
Section seven: Modifications to the contract/concession
seven.1) Description of the procurement after the modifications
seven.1.1) Main CPV code
- 45233120 - Road construction works
seven.1.3) Place of performance
NUTS code
- UKG - West Midlands (England)
seven.1.4) Description of the procurement:
To deliver the A457 Dudley Road scheme.
The Council's aspirations and objectives for the scheme remain unchanged and focus on improving journey times, reducing congestion, and enhancing public transport and active modes along the corridor. Improved journeys for a variety of modes will also improve the attractiveness of the area, stimulating economic
growth through enabling access to key development sites which will help to bring forward approximately 3,000 new homes along with other local facilities and employment opportunities. This in turn will support and protect the city's growth objectives within the Greater Icknield area.
In addition, the A457 Scheme provides improvements for public transport, pedestrians and cyclists to align with the Emergency Transport Plan and Active Travel Plan introduced following Covid-19 and aspires towards the longer-term priorities of the Council in terms of sustainable transport and working towards net zero carbon by 2030.
seven.1.5) Duration of the contract, framework agreement, dynamic purchasing system or concession
Duration in months
36
seven.1.6) Information on value of the contract/lot/concession (excluding VAT)
Total value of the contract/lot/concession:
£32,135,000
seven.1.7) Name and address of the contractor/concessionaire
McPhillips (Wellington) Ltd
Horton House, Hortonwood 50
Telford
TF1 7FG
Country
United Kingdom
NUTS code
- UKG - West Midlands (England)
Justification for not providing organisation identifier
Not on any register
The contractor/concessionaire is an SME
No
seven.2) Information about modifications
seven.2.1) Description of the modifications
Nature and extent of the modifications (with indication of possible earlier changes to the contract):
The proposed contract modification for additional works have become necessary the design changes as a result of new government policies regarding sustainable transport; the latest LTN 1/20 design guidance which came into operation during the contract period; the imposed time constraints from the funding conditions. As a consequence, Phases 5 and
6 are required to be completed incorporating a modification to the existing contract.
The Council is seeking to undertake these in accordance with PCR 2015 Regulation 72(b)(ii) where a change of contractor 'would cause significant inconvenience or substantial
duplication of costs for the contracting authority' This increase would cause the contract value to exceed the 50% tolerance. However, the Council will publish a notice in accordance with PCR 2015, Regulation 72(3) and as a further mitigation of additional cost increases will separately tender Phase 7.
seven.2.2) Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire.
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
The proposed contract modification for additional works have become necessary the design changes as a result of new government policies regarding sustainable transport; the latest LTN 1/20 design guidance which came into operation during the contract period; the imposed time constraints from the funding conditions. As a consequence, Phases 5 and
6 are required to be completed incorporating a modification to the existing contract.
seven.2.3) Increase in price
Updated total contract value before the modifications (taking into account possible earlier contract modifications, price adaptions and average inflation)
Value excluding VAT: £32,135,000
Total contract value after the modifications
Value excluding VAT: £37,102,000