Section one: Contracting authority
one.1) Name and addresses
University of Essex
University of Essex
Wivenhoe Park
CO4 3SQ
Contact
Aston Baker
Country
United Kingdom
Region code
UKH3 - Essex
Internet address(es)
Main address
one.3) Communication
The procurement documents are available for unrestricted and full direct access, free of charge, at
https://supplierlive.proactisp2p.com/Account/Login
Additional information can be obtained from the above-mentioned address
one.4) Type of the contracting authority
Body governed by public law
one.5) Main activity
Education
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Decarbonisation Consultant - Soft Market Testing 2023
Reference number
DN1540
two.1.2) Main CPV code
- 71313000 - Environmental engineering consultancy services
two.1.3) Type of contract
Services
two.1.4) Short description
The University requires a plan setting out the enhancements required to its built environment, to realise its aspirations and to formalise its journey to net zero scope 1 and 2 carbon emissions by 2035. The University also wishes to gain clarity what capital will be required to achieve net zero scope 1 and 2 carbon emissions by 2035 and as the estates heating is decarbonised, how the energy mix will alter.
The requirements are split across four parts as follows:
• Part 1 - Detailed scoping of buildings across three campuses.
• Part 2 - Carbon management/decarbonisation plan.
• Part 3 - Energy mix exercise as heating is decarbonised.
two.1.6) Information about lots
This contract is divided into lots: No
two.2) Description
two.2.2) Additional CPV code(s)
- 90713000 - Environmental issues consultancy services
- 71314300 - Energy-efficiency consultancy services
two.2.3) Place of performance
NUTS codes
- UKH3 - Essex
two.2.4) Description of the procurement
The University requires a plan setting out the enhancements required to its built environment, to realise its aspirations and to formalise its journey to net zero scope 1 and 2 carbon emissions by 2035. The University also wishes to gain clarity what capital will be required to achieve net zero scope 1 and 2 carbon emissions by 2035 and as the estates heating is decarbonised, how the energy mix will alter.
The requirements are split across four parts as follows:
• Part 1 - Detailed scoping of buildings across three campuses.
• Part 2 - Carbon management/decarbonisation plan.
• Part 3 - Energy mix exercise as heating is decarbonised.
two.3) Estimated date of publication of contract notice
2 October 2023
Section four. Procedure
four.1) Description
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: Yes