Section one: Contracting authority
one.1) Name and addresses
Associated British Ports
25 Bedford Street
London
WC2E 9ES
Contact
Group Procurement
Country
United Kingdom
NUTS code
UKE13 - North and North East Lincolnshire
Internet address(es)
Main address
https://in-tendhost.co.uk/abp/aspx/Tenders/Current
Buyer's address
https://in-tendhost.co.uk/abp/aspx/Tenders/Current
one.3) Communication
Additional information can be obtained from the above-mentioned address
one.4) Type of the contracting authority
Other type
Utility
one.5) Main activity
Other activity
Port Operator
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Modifications to Henderson Dry Dock at the Port of Immingham
two.1.2) Main CPV code
- 45240000 - Construction work for water projects
two.1.3) Type of contract
Works
two.1.4) Short description
Procurement of the Principal Contractor for the design and construction of works to modify Henderson Dry Dock, remove RORO (Roll On Roll Off) ramps, partially demolish the sill and undertake remodelling works required to the quay. Please respond to this PIN by email to procurement@abports.co.uk
two.1.6) Information about lots
This contract is divided into lots: Yes
two.2) Description
two.2.1) Title
Modifications to Henderson Dry Dock at the Port of Immingham Including Increasing the Depth
Lot No
1
two.2.2) Additional CPV code(s)
- 45240000 - Construction work for water projects
- 45244000 - Marine construction works
- 45241100 - Quay construction work
- 45241400 - Dock construction work
- 45213342 - Ro-ro terminal construction work
two.2.3) Place of performance
NUTS codes
- UKE13 - North and North East Lincolnshire
Main site or place of performance
Port of Immingham
two.2.4) Description of the procurement
The aim of this project is to increase the draft of vessels can be accommodated in Henderson Dry Dock. The design and construction works to be undertaken by the principal contractor will include, but are not limited to the following main elements: Completion of the design. The Contractor will complete the design of the permanent works and undertake the full design and detail of the temporary works including shoring of the HDD (Henderson Dry Dock) walls and cofferdam. Site establishment and preparations. Construction Works - Installing a cofferdam to the front of the Dry Dock; - Pumping out the Dry Dock; - Install temporary works to restrain dry dock walls - Remove and dispose of the remaining sediment to the base of the dry dock; - Break out and remove sill; - Increase the depth of the dry dock by approximately 1m by means of breaking out or planning concrete; - Removal and disposal of the RORO ramps (concrete slab over steel ramp); - Extend broken back dry dock walls (under RORO Ramp) to ground level and make good surrounding paving; - Associated mooring / quay furniture - Removal of cofferdam and other temporary works; - Performance monitoring of the new structure including undertaking surveys during the defects period.
two.2) Description
two.2.1) Title
Modifications to Henderson Dry Dock at the Port of Immingham Excluding Works Associated with Increasing the Depth
Lot No
2
two.2.2) Additional CPV code(s)
- 45240000 - Construction work for water projects
- 45244000 - Marine construction works
- 45241100 - Quay construction work
- 45241400 - Dock construction work
- 45213342 - Ro-ro terminal construction work
two.2.3) Place of performance
NUTS codes
- UKE13 - North and North East Lincolnshire
two.2.4) Description of the procurement
The aim of this project is to modify Henderson Dry Dock to meet business requirements without increasing the depth. The design and construction works to be undertaken by the principal contractor will include, but are not limited to the following main elements: Completion of the design. The Contractor will complete the design of the permanent works and undertake the full design and detail of the temporary works. Site establishment and preparations. Construction Works - Install temporary works to allow breaking out of sill; - Break out and remove sill; - Removal and disposal of the RORO ramps (concrete slab over steel ramp); - Extend broken back Dry dock walls (under RORO Ramp) to ground level and make good surrounding paving; - Removal of temporary works;- Associated mooring / quay furniture
two.3) Estimated date of publication of contract notice
5 September 2023
Section four. Procedure
four.1) Description
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: No