Section one: Contracting entity
one.1) Name and addresses
Dover Harbour Board
Harbour House,Marine Parade
DOVER
CT179BU
Contact
Louise Hooley
DWDRprocurement@doverport.co.uk
Telephone
+44 1304240400
Country
United Kingdom
Region code
UKJ44 - East Kent
Justification for not providing organisation identifier
Not on any register
Internet address(es)
Main address
one.3) Communication
Additional information can be obtained from the above-mentioned address
one.6) Main activity
Port-related activities
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Dover Western Docks Revival Project - Reclamation works to infill Granville Dock, Tidal Basin, and Wick Channel
two.1.2) Main CPV code
- 45000000 - Construction work
two.1.3) Type of contract
Works
two.1.4) Short description
As part of the final stages of the large-scale Dover Western Docks Revival (DWDR) project, in the Port of Dover, we wish to carry out site clearance works of the existing pontoons and restraint piles, decommission two sets of lock gates and a Swingbridge and carry out reclamation works to infill the old Granville Dock, Tidal Basin, and Wick Channel.
To contain the reclamation material, approx. 1,000,000m3, we also need to construct two quay walls totalling approx. 130m in linear length.
Other ancillary works include extension of existing storm water and foul water drainage networks and rationalisation of existing HV, LV and data networks to provide services for future development on top of the approx. 10 hectares of newly created Port land.
two.1.6) Information about lots
This contract is divided into lots: No
two.2) Description
two.2.2) Additional CPV code(s)
- 45111100 - Demolition work
- 45111200 - Site preparation and clearance work
- 45111290 - Primary works for services
- 45112300 - Infill and land-reclamation work
- 45112310 - Infill work
- 45112320 - Land-reclamation work
- 45241100 - Quay construction work
- 45241400 - Dock construction work
- 45244000 - Marine construction works
- 45252124 - Dredging and pumping works
two.2.3) Place of performance
NUTS codes
- UKJ44 - East Kent
Main site or place of performance
Port of Dover
two.2.4) Description of the procurement
As part of the final stages of the large-scale Dover Western Docks Revival (DWDR) project, in the Port of Dover, we wish to carry out site clearance works of the existing pontoons and restraint piles, decommission two sets of lock gates and a Swingbridge and carry out reclamation works to infill the old Granville Dock, Tidal Basin, and Wick Channel.
To contain the reclamation material, approx. 1,000,000m3, we also need to construct two quay walls totalling approx. 130m in linear length.
Other ancillary works include extension of existing storm water and foul water drainage networks and rationalisation of existing HV, LV and data networks to provide services for future development on top of the approx. 10 hectares of newly created Port land.
two.2.14) Additional information
For queries regarding this project and the planned procurement procedure, interested contractors are invited to contact;
DWDRprocurement@doverport.co.uk
for more information quoting the works reference;
Dover Western Docks Revival Project - Reclamation works to infill Granville Dock, Tidal Basin, and Wick Channel
two.3) Estimated date of publication of contract notice
1 October 2022
Section four. Procedure
four.1) Description
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: No
four.2) Administrative information
four.2.4) Languages in which tenders or requests to participate may be submitted
English
Section six. Complementary information
six.3) Additional information
For queries regarding this project and the planned procurement procedure, interested contractors are invited to contact;
DWDRprocurement@doverport.co.uk
for more information quoting the works reference;
Dover Western Docks Revival Project - Reclamation works to infill Granville Dock, Tidal Basin, and Wick Channel