Award

PE0715 Wavenet –Managed Internet Service and Cabling

  • Peabody

UK5: Transparency notice - Procurement Act 2023 - view information about notice types

Notice identifier: 2025/S 000-019827

Procurement identifier (OCID): ocds-h6vhtk-050f18

Published 8 May 2025, 4:08pm



Scope

Reference

PE0711- Cxxx

Description

Wavenet will be providing a fully managed internet service for the site at New Mansion

Square which consists of providing connectivity to the commercial units (tech hub, cultural

unit, 11 other units + 1 more in future) and the residents longue (coworking, cinema

room, phone booths)

Following the cablers recent site survey, it has been identified that additional cabling

infrastructure is required to support the delivery of a managed connectivity solution.

The existing cabling infrastructure is only suitable for BT's FTTP network, which is residential

in nature and does not support the service levels or resilience expected of a business-grade

managed service.

In order to deliver on the brief, the following works need to be carried out:

Cabling

• Cables linking each unit to the Main IT Room

• 1 x cable will be run from the Main IT room to each of the 14 units in scope

• Cables will be 4 core fibre

• Cables will be run using existing routes - roof voids, cable trays, and underground

ducting

• Internal cables will be tight buffer internal type

• External cables will be CST armoured protected

• 1 x LC 4 Duplex fibre tray will be installed in each of the in-unit comms cabinets

Units 1 and 2

• Although not currently in scope, a cable will be run to the marketing suite to save cost

and complexity in future

• If the suite is not accessible, the cable can be left coiled and secure nearby, ready for

installation when this unit is being refurbished

Main IT Room

A new cabinet will be installed to keep our equipment safe and segregated from other contractors

This will be a 20u floor standing cabinet (800mm x 800mm)

1 x LC 48 Duplex fibre tray will be installed

1 x 6way PDU will be installed. This will connect to the Commando unit - currently not in-use

Cabling for WiFi Access Points (APs)

In the resident's lounge and the tech hub, a single Cat6 cable will need to be installed for connecting the AP

This will be run from the in-unit cabinet to the ceiling, where the AP will be installed

In all of the other units, the APs will be wall mounted to save on additional cabling work

Wavenet will be providing a fully managed internet service for all commercial units as mentioned above.

Wired and wireless internet access on day 1 for all incoming tenants

Fully managed support

Scalable service which can be replicated at other sites

Once the cables have been linked they will install a 10Gb bearer with 1Gb bandwidth. This will allow Peabody to increase capacity to 10Gb at anytime.

They will install the infrastructure which consists of 10Gb firewall, which will meet the requirements of content filtering.

Wifi

WiFi experience includes: secure access, private networks, roaming (the ability to stay

connected across the entire site), and analytics.

Monitoring and Analytics

Wavenet will have visibility of the network health and performance and proactively resolve issues. All systems will provide visibility, insights and reports to our teams.

Remote and Onsite Engineers

Helpdesk and 24 / 7 Network Operations Centre (NOC)

Proactive Network Monitoring

Performance optimisation

Incident Response and Troubleshooting

Documentation and Reporting

Wavenet Limited shall perform the services to provide connectivity to the commercial units mentioned as described in their proposal Schedule 2 (Wavenet Connected Proposal for Peabody) Option A - Enterprise Switches and Opex costs.

Due to the existing cables not being suitable and tenants moving in quickly Peabody require a temporary solution to be put in place as mentioned in the Temporary Connectivity - Option 2 1GB Wireless Leased Line, this will be retained as a backup service.

To view this notice, please click here:

https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=945648319


Contract 1

Supplier

Contract value

  • £102,753.12 excluding VAT
  • £123,303.74 including VAT

Below the relevant threshold

Earliest date the contract will be signed

10 May 2025

Contract dates (estimated)

  • 10 May 2025 to 9 May 2028
  • 3 years

Main procurement category

Services

CPV classifications

  • 32412110 - Internet network
  • 32521000 - Telecommunications cable
  • 48221000 - Internet browsing software package
  • 72400000 - Internet services
  • 72411000 - Internet service providers ISP

Contract locations

  • UKI - London

Procedure

Procedure type

Below threshold - without competition


Supplier

Wavenet

Blythe Valley Park,, One Central Blvd,, Blythe Valley Park

SOLIHULL

B90 8BG

United Kingdom

Telephone: 0333 234 0011

Email: contact@wavenet.co.uk

Region: UKG32 - Solihull

Small or medium-sized enterprise (SME): No

Voluntary, community or social enterprise (VCSE): No

Contract 1


Contracting authority

Peabody

  • Public Procurement Organisation Number: PYJY-3925-DVJD

45 Westminster Bridge Rd

London

SE1 7JB

United Kingdom

Contact name: Yvonne Chukwuemeka

Email: yvonne.chukwuemeka@peabody.org.uk

Region: UKI44 - Lewisham and Southwark

Organisation type: Public authority - sub-central government