HE0914 A350 Chippenham Duelling Scheme April 2023

  • Wiltshire Council

F14: Notice for changes or additional information

Notice identifier: 2023/S 000-014764

Procurement identifier (OCID): ocds-h6vhtk-037589

Published 24 May 2023, 11:58am



Section one: Contracting authority/entity

one.1) Name and addresses

Wiltshire Council

Wiltshire Council, County Hall, Bythesea Road

Trowbridge

BA14 8JN

Contact

Mr David Gillett

Email

david.gillett@wiltshire.gov.uk

Country

United Kingdom

Region code

UKK15 - Wiltshire CC

Internet address(es)

Main address

http://www.wiltshire.gov.uk/

Buyer's address

http://www.wiltshire.gov.uk/


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

HE0914 A350 Chippenham Duelling Scheme April 2023

Reference number

DN637737

two.1.2) Main CPV code

  • 45233100 - Construction work for highways, roads

two.1.3) Type of contract

Works

two.1.4) Short description

The A350 is one of the most important routes in Wiltshire. It is a primary north-south route

with regional significance connecting the south coast with the M4 and onwards to Bristol

and the Midlands. In Wiltshire it passes around the principal settlements of Chippenham and

Trowbridge via the town of Melksham and on to Westbury and Warminster.

It has been a longstanding priority to improve north-south connectivity along the A350, and

Wiltshire Council has been progressively bringing forward the dualling of the A350

Chippenham bypass.

Over recent years three major capital schemes (Phases 1, 2 and 3) have been brought

forward to improve capacity and safety on the route, largely funded through successful

Department for Transport (DfT) and/or Local Enterprise Partnerships (LEP) funding bids.

Most recently, an Outline Business Case (OBC) bid was made to DfT for funding to bring

forward a scheme to complete the dualling of the A350 bypass at Chippenham.

In the spending review in October 2021 the government announced that it would allocate

funds for a scheme to dual the remaining single carriageway sections of the A350 route

round Chippenham.

The project was also included within the list of forthcoming infrastructure projects as part of The Growth Plan 2022 published in September 2022.

Wiltshire Council and its consultants Atkins are now pressing forward to complete the

design of the remaining Phases 4 and 5 of the scheme and preparing the Full Business Case

(FBC). Subject to the FBC being approved by the DfT, it is anticipated that construction

works will be undertaken during 2024 and 2025.


Section six. Complementary information

six.6) Original notice reference

Notice number: 2023/S 000-012215


Section seven. Changes

seven.1.2) Text to be corrected in the original notice

Section number

IV.2.2

Place of text to be modified

Time limit for receipt of tenders or requests to participate

Instead of
Date

30 May 2023

Local time

12:00pm

Read
Date

31 May 2023

Local time

12:00pm