Southern Integrated Delivery (SID) - B&C and E&P

  • Network Rail Infrastructure Ltd

F14: Notice for changes or additional information

Notice reference: 2023/S 000-010223

Published 6 April 2023, 3:53pm



Section one: Contracting authority/entity

one.1) Name and addresses

Network Rail Infrastructure Ltd

Waterloo General Offices

London

SE1 8SW

Contact

Matthew McCarty

Email

SouthernCP7Delivery@NetworkRail.co.uk

Telephone

+44 1908781000

Country

United Kingdom

NUTS code

UKJ - South East (England)

Internet address(es)

Main address

http://www.networkrail.co.uk/


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

Southern Integrated Delivery (SID) - B&C and E&P

two.1.2) Main CPV code

  • 45000000 - Construction work

two.1.3) Type of contract

Works

two.1.4) Short description

Network Rail has carried out a procurement exercise to award the CP7 Southern Integrated Delivery (SID) agreement to deliver our Control Period 7 (CP7) and potentially CP8 renewals portfolio.

The SID will be a fully integrated team based on 'Project 13' principles comprising all categories of railway assets: Signalling, Track, Buildings & Civils (B&C), Electrification and Plant (E&P) and Minor Works. The scope includes the following items: development, design, manufacture, supply, installation, integration, testing and commissioning of the Southern renewals work bank.

These works will be undertaken on Kent, Sussex and Wessex routes, and will primarily be focused on the delivery of the renewals portfolio, however options will be included to enable enhancements also to be delivered, subject to capacity and where the SID is considered the optimum procurement route.

This notice covers the appointment of the Buildings & Civils (Lot 1) and Electrification & Plant (Lot 2) lots, where all appointed Business Partners within the SID have initially signed into a development phase agreement, scheduled from February 2023 to April 2024. The main SID agreement will be 10 years in duration (April 2024 - March 2034) and will commence in CP7 with the inclusion of a break clause prior to the commencement of CP8.


Section six. Complementary information

six.6) Original notice reference

Notice number: 2023/S 000-007899


Section seven. Changes

seven.1.2) Text to be corrected in the original notice

Section number

V.2.1)

Lot No

1

Place of text to be modified

(dd/mm/yyyy)

Instead of
Date

15 February 2023

Read
Date

31 March 2034

Section number

V.2.1)

Lot No

2

Place of text to be modified

(dd/mm/yyyy)

Instead of
Date

15 February 2023

Read
Date

31 March 2034