Section one: Contracting authority
one.1) Name and addresses
Associated British Ports
Associated British Ports, PO Box 1
Hull
HU9 5PQ
Contact
Group Procurement Team
Country
United Kingdom
NUTS code
UKE13 - North and North East Lincolnshire
Internet address(es)
Main address
https://in-tendhost.co.uk/abp/aspx/Tenders/Current
Buyer's address
https://in-tendhost.co.uk/abp/aspx/Tenders/Current
one.3) Communication
Additional information can be obtained from the above-mentioned address
one.4) Type of the contracting authority
Other type
Port Authority
one.5) Main activity
Other activity
Port Authority
Section two: Object
two.1) Scope of the procurement
two.1.1) Title
Project Sugar, Immingham - Land Side_Marine Side | Civils_Structural
Reference number
ABP-HUM-22/0329
two.1.2) Main CPV code
- 45220000 - Engineering works and construction works
two.1.3) Type of contract
Works
two.1.4) Short description
Construction of 2 new harbour berths over a minimum of 46 acresAvailability intends to expand to 4 berths with additional storage land. RoRo_RoPax Vessels (low Pax levels) trafficTerminal Building constructionEngineering Workshop constructionPre-Check in Parking areaIn/Out "Gates"Ancillary infrastructure to facilitate the running of the terminal. Operational go live date May 2025BCP facilities to suit cargo throughput
two.1.5) Estimated total value
Value excluding VAT: £100,000,000
two.1.6) Information about lots
This contract is divided into lots: No
two.2) Description
two.2.2) Additional CPV code(s)
- 45220000 - Engineering works and construction works
two.2.3) Place of performance
NUTS codes
- UKE13 - North and North East Lincolnshire
Main site or place of performance
Immingham Port
two.2.4) Description of the procurement
Construction of 2 new harbour berths over a minimum of 46 acresAvailability intends to expand to 4 berths with additional storage land. RoRo_RoPax Vessels (low Pax levels) trafficTerminal Building constructionEngineering Workshop constructionPre-Check in Parking areaIn/Out "Gates"Ancillary infrastructure to facilitate the running of the terminal. Operational go live date May 2025BCP facilities to suit cargo throughput
two.3) Estimated date of publication of contract notice
1 August 2022
Section four. Procedure
four.1) Description
four.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: No