Contract

Replacement control system for Hauzer TechCoating PVD Unit

  • Sheffield Hallam University

F03: Contract award notice

Notice identifier: 2022/S 000-007584

Procurement identifier (OCID): ocds-h6vhtk-03243a

Published 21 March 2022, 1:54pm



Section one: Contracting authority

one.1) Name and addresses

Sheffield Hallam University

City Campus,Howard Street

SHEFFIELD

S11WB

Contact

Procurement Team

Email

strategicprocurement@shu.ac.uk

Telephone

+44 1142253431

Country

United Kingdom

NUTS code

UKE32 - Sheffield

Internet address(es)

Main address

https://www.shu.ac.uk/

one.4) Type of the contracting authority

Body governed by public law

one.5) Main activity

Education


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

Replacement control system for Hauzer TechCoating PVD Unit

Reference number

CW204-LW

two.1.2) Main CPV code

  • 51430000 - Installation services of laboratory equipment

two.1.3) Type of contract

Services

two.1.4) Short description

There is no other option to keep the coating unit running and bring it up to the most recent safety standards. Replacing the control system for this unit would be a fraction of the cost of an entire new unit. The cost of a new unit would be over £1.2M and would not include the bespoke modifications that the current system has. Major components of the unit have already been replaced e.g. pumping units at a cost of £139k, which were replaced in 2017.

Only the original equipment manufacturer is capable of replacing the control system for the this highly complex industrial machine. SHU tendered for replacement pumps for the machine in 2016/17 (1617-05-ACES-JM) and only Hauzer returned a submission. It would have been significantly easier to a third party to reverse-engineer the pump requirements than it would for a company to reverse engineer the control system. An analogy would be that replacing the pumps is like a lung transplant, replacing the control system is like a brain transplant. The first is very difficult, the second impossible.

two.1.6) Information about lots

This contract is divided into lots: No

two.1.7) Total value of the procurement (excluding VAT)

Value excluding VAT: £200,000

two.2) Description

two.2.3) Place of performance

NUTS codes
  • UKE32 - Sheffield

two.2.4) Description of the procurement

There is no other option to keep the coating unit running and bring it up to the most recent safety standards. Replacing the control system for this unit would be a fraction of the cost of an entire new unit. The cost of a new unit would be over £1.2M and would not include the bespoke modifications that the current system has. Major components of the unit have already been replaced e.g. pumping units at a cost of £139k, which were replaced in 2017.

Only the original equipment manufacturer is capable of replacing the control system for the this highly complex industrial machine. SHU tendered for replacement pumps for the machine in 2016/17 (1617-05-ACES-JM) and only Hauzer returned a submission. It would have been significantly easier to a third party to reverse-engineer the pump requirements than it would for a company to reverse engineer the control system. An analogy would be that replacing the pumps is like a lung transplant, replacing the control system is like a brain transplant. The first is very difficult, the second impossible.

two.2.5) Award criteria

Price

two.2.11) Information about options

Options: No


Section four. Procedure

four.1) Description

four.1.1) Type of procedure

Award of a contract without prior publication of a call for competition in the cases listed below

  • The procurement falls outside the scope of application of the regulations

Explanation:

COMPETITION WAIVER - There is no other option to keep the coating unit running and bring it up to the most recent safety standards. Replacing the control system for this unit would be a fraction of the cost of an entire new unit. The cost of a new unit would be over £1.2M and would not include the bespoke modifications that the current system has. Major components of the unit have already been replaced e.g. pumping units at a cost of £139k, which were replaced in 2017.

Only the original equipment manufacturer is capable of replacing the control system for the this highly complex industrial machine. SHU tendered for replacement pumps for the machine in 2016/17 (1617-05-ACES-JM) and only Hauzer returned a submission. It would have been significantly easier to a third party to reverse-engineer the pump requirements than it would for a company to reverse engineer the control system. An analogy would be that replacing the pumps is like a lung transplant, replacing the control system is like a brain transplant. The first is very difficult, the second impossible.

four.1.8) Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement: No


Section five. Award of contract

Title

Replacement control system for Hauzer TechCoating PVD Unit

A contract/lot is awarded: Yes

five.2) Award of contract

five.2.1) Date of conclusion of the contract

28 January 2022

five.2.2) Information about tenders

Number of tenders received: 1

The contract has been awarded to a group of economic operators: No

five.2.3) Name and address of the contractor

IHI Hauzer Techno Coating B.V.

Van Heemskerckweg 22, 5928 LL Venlo, Netherlands

5928 LL Venlo

Country

Netherlands

NUTS code
  • NL - Netherlands
The contractor is an SME

No

five.2.4) Information on value of contract/lot (excluding VAT)

Initial estimated total value of the contract/lot: £200,000

Total value of the contract/lot: £200,000


Section six. Complementary information

six.4) Procedures for review

six.4.1) Review body

Sheffield Hallam University

Sheffield

Country

United Kingdom