Structural Engineering services

  • Britten Pears Arts

F14: Notice for changes or additional information

Notice identifier: 2024/S 000-000205

Procurement identifier (OCID): ocds-h6vhtk-0429fe

Published 4 January 2024, 12:02pm



Section one: Contracting authority/entity

one.1) Name and addresses

Britten Pears Arts

Snape Maltings Concert Hall

Saxmundham

IP17 1SP

Contact

Ken Baines

Email

kbaines@brittenpearsarts.org

Telephone

+44 7970161832

Country

United Kingdom

Region code

UKH14 - Suffolk

Companies House

00980281

Internet address(es)

Main address

www.brittenpearsarts.org


Section two: Object

two.1) Scope of the procurement

two.1.1) Title

Structural Engineering services

two.1.2) Main CPV code

  • 71312000 - Structural engineering consultancy services

two.1.3) Type of contract

Services

two.1.4) Short description

Structural Engineering Services RIBA Stages 0 - 7 across multiple workstreams as described in the Invitation to Tender


Section six. Complementary information

six.6) Original notice reference

Notice number: 2023/S 000-037983


Section seven. Changes

seven.1) Information to be changed or added

seven.2) Other additional information

Tender Clarification Number 1 following tender query.

Q1. We note that at Section 3 / Questionnaire (Item 8.1a) you are seeking a commitment to Professional Indemnity Insurance to a level of £10,000,000 which does seem high for the scope of structural work involved. Was there a specific area of the programme that you felt warranted this level of cover? We note that this is a pass/fail section of the Tender so would not wish to jeopardise our bid by not committing but we are looking to understand where this level of cover would be required.

A1. The works under workstream CH1 include the need for additional structural support to the Concert Hall roof. The works under under workstream BP1 include removal of walls which may be load bearing and additional structural support to the studio roof. It was considered that £5M would not be adequate cover as it does not just relate to project construction value and the level of £10M set provided the cover necessary and therefore adjustment to a lower level is not acceptable.