Fulwood Bridge Painting
- VIA EAST MIDLANDS LIMITED
Procurement identifier (OCID): ocds-h6vhtk-0683f4
Description
The works shall consist of the preparation and repainting of Fulwood Bridge on the A38 in Sutton in Ashfield, Nottingham.
The bridge is a twin deck structure with the section to be painted being the three span steel lattice girder bridge on the north side. Spans to the bridge consist of two side spans measuring 13.3m and a central span of 17.1m. 4x no. lattice girders present connected via cross bracing and supporting a steel trough deck which also requires painting. Lattice girders supported on blue brick piers and abutments. Height of piers to the lattice girders is up to 6.2m
Notices
UK7: Contract details notice
- Notice identifier
- 2026/S 000-059305
- Published
- 24 June 2026, 11:15am
UK6: Contract award notice
- Notice identifier
- 2026/S 000-051895
- Published
- 2 June 2026, 1:38pm
UK4: Tender notice
- Notice identifier
- 2026/S 000-034593
- Published
- 16 April 2026, 11:38am