Procurement

Site Waste Clearance Bolton House Road

  • Wigan Council

Procurement identifier (OCID): ocds-h6vhtk-05ec24

Description

Wigan Council is seeking a suitably qualified contractor to clear waste illegally deposited on Diggle Flash Nature Reserve adjacent to Bolton House Road, Bickershaw, Wigan, WN2 4AB. The procurement is being undertaken using reduced timescales due to a state of urgency in accordance with Regulation 54 of the Procurement Act 2023. This is in order reduce the environmental impact and fire risk and therefore complies with the Cabinet Office Guidance: Time Limits (note 13).

Wigan Council has committed to remove waste that has been deposited on Diggle Flash (a nature reserve) to the rear (or east of the Bolton House Road Site) and some waste will remain on the adjacent Bolton House Road site.

The quantity of waste Wigan Council expects to be removed is estimated to be 3,243 tonnes. The contractor will be responsible for all aspects of management, access, construction, security, health and safety, environmental protection, haulage/treatment and restoration.

The Bolton House Road site is subject to a closure order (granted 18th July 2025). Access to the site is strictly controlled. Contractors appointed by Wigan Council are permitted to work on the Bolton House Road site with the landowner's permission. The contractor is expected to access the site via the Smith's Lane nature reserve-Diggle Flash footpath, which will involve establishing an access route. The access route is a narrow track approximately 750 metres long that will require overgrowth/trees and canopy removal along it's length to allow HGV access, and a small area of trees will also need to be removed to allow access from the track to the area where the waste is deposited. The waste will need to be loaded onto haulage vehicles for transfer to permitted disposal. Following disposal the remaining waste will need to be reprofiled and the area left safe, which may also require land remediation.

The project will therefore involve the following steps:

1) Phase 1 - Site Preparation and Access

a. Health and Safety

b. Environmental Protection

c. Site Security and Welfare

2) Phase 2 - Arboriculture works and ground protection#

a. Vegetation removal

b. Temporary road surface

3) Phase 3 - Excavation, loading and waste treatment

a. Excavation and loading

b. Haulage and waste disposal

4) Phase 4 - Safe Site Reprofiling and Public Safety

Notices

UK4: Tender notice

Notice identifier
2026/S 000-001174
Published
7 January 2026, 3:41pm

UK2: Preliminary market engagement notice

Notice identifier
2025/S 000-078573
Published
1 December 2025, 3:24pm