Manufacturing, Technology and Skills Centre Construction Works
- Weston College
Procurement identifier (OCID): ocds-h6vhtk-055323
Description
The successful provider will be appointed to deliver comprehensive construction management and refurbishment services, including the appointment and coordination of all required specialist sub-contractors, to ensure the timely delivery of the new MTSC at Filton.
The estimated overall contract value will be between £1.75m and £2.97m and will not exceed £2.97m. The final project value is dependent on the level of funding secured through an Office for Students (OfS) bid, the outcome of which is expected end of September 2025. Two options are therefore envisaged: Option A, subject to the successful award of bid funding, and Option B, to be delivered without bid funding, with the scope and value adjusted accordingly.
Below details overall budget for Option A and Option B:
Option A - with OfS Grant - £4,5m
Option B - College Funding Only - £2,6m
Estimated construction value [excluding Fees, VAT.
Option A - with OfS Grant - £2,97m
Option B - College Funding Only - £1,75m
Start Date on site
Option A - with OfS Grant - 19/01/26
Option B - College Funding Only - 06/03/26
Completion of the construction works
Option A - with OfS Grant - 31/08/26
Option B - College Funding Only - 31/08/2026
Site Weeks
Option A - with OfS Grant - 32 week, The contractor will be on site to support the college during the moving in period.
Option B - College Funding Only - 25 weeks, The contractor will be on site to support the college during the moving in period.
Notices
UK4: Tender notice
- Notice identifier
- 2025/S 000-060463
- Published
- 29 September 2025, 12:18pm
29 September 2025, 12:18pm (latest version)
- 24 September 2025, 10:37am
UK1: Pipeline notice
- Notice identifier
- 2025/S 000-034965
- Published
- 25 June 2025, 10:46am